How Long Does It Take to Get a Building Permit?

In Moldova, a building permit must be issued within a maximum of 30 days after the application is officially registered.

To obtain the permit, the applicant must submit the application together with the required project documents. The relevant authority checks the documents and makes sure the planned construction complies with urban planning and building requirements.

The 30 day period applies to the issuing of the permit itself. Preparing the project, collecting the required documents and making any necessary corrections can take additional time.

That is why it is better to prepare the project and documents in advance. A complete and properly prepared application can help avoid unnecessary delays.